News that Dogger bank D green hydrogen element is not being pursued now comes after the announcement that the Creyke Beck offshore substation had been consented on 1 March. it led partners Equinor and Scottish and Southern Energy (SSE) to state:

“With the confirmation of an onshore grid connection location in the East Riding of Yorkshire, the option to direct the wind energy produced by Dogger Bank D towards hydrogen production, as publicly consulted on in Autumn 2023, has been retired from the project.”

Offshore Wind and Hydrogen

 

 

 

 